Expand my Community achievements bar.

Do you have questions about the migration to Adobe Business Platform? Come join our upcoming coffee break and ask away!

Durations

Avatar

Level 2
I have a project that is displaying Duration in hours for some parent tasks and Duration in days for other parent tasks. Is there a default setting I am missing to have all parent task durations display in Days? Helen McLaughlin - CapabilitySource CapabilitySource
2 Replies

Avatar

Level 3
I have seen this before on projects that have been imported from MS Project. The easiest way I have found to reset it is to edit the duration on the parent task and change it (to 0d). It will recalculate to the correct value and it should revert to days. Dale Whitchurch Arthrex Inc

Avatar

Level 2
Thanks Dale. This project may have been imported. Helen McLaughlin - CapabilitySource CapabilitySource