Duration average of projects in a program

Avatar

Level 2
Is there a way to calculate the average actual duration of projects in a program? Noah Wong BIOTRONIK, Inc.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 8
If I'm understanding you correctly, something like this? It's a project report, grouped by Program Name and with a filter on percent complete. When you add a numeric column (like actual duration) to a report, you choose how it summarises. While most often you'll choose 'Sum', in this case I chose 'Average'. Barry Buchanan Work Management Australia