Critical Path in a Template

Avatar

Level 10
Hi In a Project there is a column view for Status Icons that indicates Red when a task is on the critical path. I'm looking for something similar in the template view but I can't find anything other than the Gant view, which is not what I'm hoping for. Has anybody found the column name that shows the critical path as an Icon in a template view? Thanks! Jill Ackerman
2 Replies

Avatar

Level 8
Not sure if there's one out of the box, but you can modify / create a view and add a column for 'template task' -> 'Is critical'. It returns true or false. You could even add a rule to replace true with a symbol. Barry Buchanan - WMA Work Management Australia