Does anyone have experience breaking out their Ad-Hoc hours vs. Plan Hours projects? I am currently using the Resource Planner to calculate available hours vs. Planned hours. However, it does not tell the full story. I would like to see out of the "Planned Hours", how many were "ad-hoc" hours? Do I build Ad-Hoc project templates or build a custom form which they would use to "click" ad-hoc. This would allow me to pull the report of each project? Anyone else going through this?
Topics help categorize Community content and increase your ability to discover relevant content.
Hi Chue,
Just an idea (untested), but perhaps there is a way (as is possible in our Capacity Charting solution) that you can stack the Planned Hours by "whatever you like", which in this case, could be either a Project or Task level custom parameter that denotes whether those related hours are either "ad-hoc" or something else (e.g. "project", "admin", etc.)
Regards,
Doug