Calculated Field Help: Add task fields to a Project Form

Avatar

Community Advisor

I'm having a mental lapse, is there a way to put a calculated field on the project level that adds all the values on a task-level form?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

My default is no because I have not been able to accomplish this myself. However, I'm going to follow and hope someone proves us wrong. 




View solution in original post

3 Replies

Avatar

Community Advisor

I'm pretty sure you can't reference collections in a calculated field, so going to go with a big "no" on this one. Sorry!

Avatar

Level 2

Row Groupings:

Project >> Name Task >> Name

(Filtered by tasks that Can Start)

Column Groupings:

Parent >> Name

(the equivalent of our Milestones)

and I set the Matrix settings to Show Value Column it works for a report

Someone posted this to another similar question

I would double-check https://experienceleague.adobe.com/docs/workfront/using/basics/work-with-custom-forms/add-a-custom-f...

Task should be able to be manipulated to work in a project. There has to be a way with parent objects. Just a thought.

Avatar

Correct answer by
Community Advisor

My default is no because I have not been able to accomplish this myself. However, I'm going to follow and hope someone proves us wrong.