Hello, Well there could be a few of ways to solve this. I'll start with the simplest – can you created a project template that already has the highest number of task groups (or a strong average) and then when you create a new project with the template you can simply do a bulk delete of the ones you don't need? The more difficult would be using the API because it assumes you use the API to begin with, and that you have it configured in a way to allow this. But yes Skye is correct, we have coded a way in our API to use the form selections to create a project (from a template) and then only keep the tasks we need to keep. In your case you would have a field in the custom request form to ask how many iterations you need (i.e. 1-10). And in the API code (and the code we place in the template tasks) it would remove the iterations of tasks you don't need. Based on what I know of your dilemma I'd use one of those two approaches (depending on how frequently I have to do this). But let me know if I'm missing another variable in your scenario. Vic Alejandro, PMP, CSM | IT | Sr. IT Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/">
http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT