Billability % – Has anyone had any luck with being able to represent the utilization or billability % of a resource by looking at available hours against actual hours billed? I was hoping the Utilization tab would achieve this but it does not. Thank you

Avatar

Level 2

We’re looking for the best way to report out on our billability % last month by job role. Inputs into the calculation would be actual hours (timesheet data) divided by net capacity (a.k.a. available hours = normal schedule minus PTO)

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 6

Hi, we solve this by a business rule that defines that each employee has to timesheet a minimum norm-time. So any type of absences are tracked on a project as well as any internal tasks. We even have a "Time on the beach" project for anything you cannot account for. With that data we can simply report on a specific project custom field called "Billability".

View solution in original post

3 Replies

Avatar

Correct answer by
Level 6

Hi, we solve this by a business rule that defines that each employee has to timesheet a minimum norm-time. So any type of absences are tracked on a project as well as any internal tasks. We even have a "Time on the beach" project for anything you cannot account for. With that data we can simply report on a specific project custom field called "Billability".

Avatar

Level 2

Thanks Chris! I appreciate the information!

Avatar

Level 2

Thank you for the example Chris!