That's what we do as well. For In Progress Tasks that had started we change the Duration to extend the Planned Completion date. This allows you to keep the Start Date accurate and also spreads out the hours over the course of the duration more accurately. For tasks that haven't started yet, we just move the Start Date to the new Start Date. Vic Alejandro, PMP, CSM | IT | Sr. IT Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/">