Anyone create a good Estimate at Completion Report?

Avatar

Level 4
We are trying to create an Estimate at Completion report that looks like this. Person Budgeted Hours Actual Hours (Inception to Date) Forecasted Hours (Today Onward) Total EAC Over/Under Tom 100 50 80 130 +30 Jerry 200 80 100 180 -20 Heathcliffe 300 150 150 300 0 Total 600 280 330 610 +10 Which is pretty similar to what is on the utilization tab (in the new release it looks like you can put budgeted hours in by person - which is good). However, I don't think the Planned hours in the Utilization change based on "when" you are running the report - I think it is the total planned hours . . this report would be perfect if Planned Hours were replaced with Planned Hours Remaining. Any ideas would be most welcome John Hoebler