Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!

Adding Project Name to Baseline Task Report

Avatar

Level 1
Hi. There may be a very simple answer to this (or maybe not!), but I want to group my baseline task report by Project Name. How do you do that?
2 Replies

Avatar

Level 1
Go ahead and try this in the grouping text mode: group.0.displayname=Project Name group.0.linkedname=task group.0.namekey=view.relatedcolumn group.0.querysort=task:project:name group.0.valuefield=task:project:name group.0.valueformat=HTML textmode=true

Avatar

Level 1
Awesome! Thanks, Zachary. It worked.