Hi @Aaron Godwin Do you need just the total number of actual hours rolled up at the parent level? If so, just add a filter for number of children greater than 0. This will exclude all the child tasks but will still show the rolled-up totals at the parent task levels.
If you need to see the individual hour records, then you can run an hour report and also filter it down (this time with number of children equals 0). The complication is that you will need to get into text mode to group it by the parent task (pretty sure that is possible). Lastly you also need your custom field contents from the parent task to be concatenated with the parent task name. I think this is also possible but don't have time to play with it right now. If you need to explore the hours report, let everyone know and they can jump in with ideas. Regards,