A project for instance "NPI - FD REF Recessed handle + black glass AU NZ UK" we have a lot of approval processes linked to tasks.
For instance Task 32. has an approval process. Although due to the Trigger being on New, the approval process is already active.
But the project in in Planning. So should that not enable the approval process to stop or to edit the approval process?
In other words can we not setup a project and test the approval process steps then change the project to current where the approvals are then active?
The workaround is to go back and fix all the task dependencies to off and then complete the tasks and then revoke/recall the task in hands approval.