Level 1

Since the recent Workfront update, my view for Workload Balancer has changed and there is new "BDG" column (which in my case is showing 0 for every role). Where can I find information on what this number is and how to input values so the data displayed is actually useful to me? Right now, the information I was getting from that view (to see variance between planned and available hours) is no longer showing up.

2 Replies

Avatar

Community Advisor

@DianaLe1 - based on the screenshot it looks like you are in the planner view and not in the Workload balancer

 

The BDG field is for budgeted hours. Budgeted Hours affect the value of the Budgeted Labor Cost (or the Resource Planner Budgeted Cost) of the project. 

 

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/project-finances/bud...

 

You can turn it off in your view if you don't use it by clicking on the 'Hours' dropdown and then customizing.

 

KellieGardner_0-1761752573144.png

 




Avatar

Administrator

@DianaLe1 Just checking in! Were you able to get this resolved? If you found your own solution, sharing the details would be a big help to others who might face the same issue later on. And if one of the replies here helped, whether it fully solved the problem or simply pointed you in the right direction, marking it as accepted makes it much easier for future readers to find. Thanks again for helping close the loop and contributing to the community!