Hi David, Just found your post when looking for the same thing that
Chrystal wanted. I like your approach, but wondering if there's any way
around Workfront blasting LATE on every task, when we only care about
the projected dates (on specific projects with no hard deadline). Or
when every person assigned, further down the task list, is now flagged
as late, when it's not their fault that their task's predecessor wasn't
completed on time. Managers review Workfront and ask, "why is everything
late?...