Interesting challenge Miranda, I'm not aware of a way to un-bulk update
in the manner you seek, but you could use our UberCalc solution (or
Fusion, if you have it) instead. Alternatively, you might consider
testing different Duration Types (e.g. Calculated Assignment vs Effort
Driven vs Calculated Work vs Simple) to see if one of them is a better
fit for your current workflow (e.g. doesn't divide the task's work by 6)
so the Workload balancer is then more useful. Regards,Doug