I have a Parent duration of 15 days. If the first child (12 day duration) is complete before the due date we want to change the start date of the second child (3 day duration) to the preceding task completion date so the assignee are not waiting until the original start date of the task to complete...
I have some tasks set monthly for projects. I could have a task for September for Mary Doe and a task for October for Mary Doe. For some reason, the task doesn't always show on the timesheet for a month. If I go in and change it from "New" to "In Process", it will normally then appear on the timeshe...