@kynabaker16 - I've tried using this code in an assignment report and it
doesn't seem to work. Wondering if it needs to be modified for this type
of report. Do you have any suggestions? I tried adding task in front of
actualWorkRequired and that didn't seem to pull anything. Thanks for any
help you can provide.
Hi Chris, What you're asking for sounds doable, and there's a good
primer on comparing fields of the same datatype here, which I invite you
to review, use, and then confirm how you make out. Regards,Doug
I know I'm late to this conversation, but we go with an even simpler
solution. I've trained our PM's to just change the Planned Hours to the
new total (including what's already been spent). In this example, change
the Planned Hours to 52. And if the task planned completion will be
extended due to this, be sure to change the Duration (not the Planned
Completion Date). This way you retain your Start Date and the planned
hours are still spread across the proper dates (or at least close). The
downsi...