Hi, Karen, this may not be the same issue but something similar happened
to me and it ended up being the start date (or completion date if you
are scheduling from completion) was not set to 8am on that date. In
other words, from 11am on 10/3 to 11am on 10/4 = 1 day. Anotgher thing
that threw me for a loop was that our company has 7.5hr work days,
however, setting up workfront with a 1/2hr in our work day threw off all
of the "whole" hours timelines. Noth sure that helps, but worth
mentioning. Go...