Tammie, We have a Project Manager Dashboard and one of the reports on
there is a task report with these filters: Projecct > Owner ID, Equal,
$$USER.ID Task > Planned Completion Date, Less Than Equal, $$TODAY+7D
Assignment Roles > ID, Is Not Blank (so it doesn't pull in parent tasks)
Project > Status, Equal, In Progress (so any projects still in planning
or on hold don't pull in) Task > Percent Complete, Less Than, 100 (so it
doesn't pull in completed tasks) OR all the above filters with a tweak
...