We have an interesting predicament. If Task 3 should always happen 20
days before Task 7, we have Task 7 linked as the connector/predecessor
to Task 3 - (Task 7 - 20 days). HOWEVER, in the Work List/Home Page,
Task 3 will show as "Not Ready" and base it on the fact that Task 7 is
not yet done. But in reality, Task 7 will never be done before Task 3,
so Task 3 should always be listed as "Ready"! Is there a setting I am
missing to fix this kind of issue? Appreciate any guidance and insights
here. ...