Tips from our PM. Make sure you are using predecessors in their
workflows, making sure that duration and hours are filled out on each
task. Make sure task constraints are not “Must happen on”,
this lock all the tasks down and makes it too hard to control the
workflow manually. (I made this mistake in the beginning and nearly went
crazy trying to do it this way) Once all of this is fixed, teach project
managers to use “recalculate timeline” to update the dates
instead of d...