More details - The problem that I am having is I have a project that
happens to be a multi-year project. It started back in 2016 and it will
continue through 2018. I need to be able to report on both the
"Budgeted" resource hours AND cost for 2016, 2017, & 2018. I also need
to report the "Actual" resource hours AND cost spent during 2016, 2017 &
2018. I am able to get the actual hours & cost by producing a matrix
"hours type" report. I do not see a way in workfront to pull "Budgeted
hours" and "...