I agree to this idea, that the status "In Progress" should be linked
with completeness %, but also logged hours should be included. In my
opinion it should not be possible to log hours and leave task status in
"New" and/or 0%. This should all be linked together. As soon as hours
are logged on a task, status must be set to "In Progress" and user must
enter % of completeness. If any of these three is not in synch, system
should prompt an error to the user, asking to enter appropriately.