Need ability for Project Managers to delete their own comments without
being able to delete others (Stakeholders, approvers, etc.). Often,
Project Managers are pretasking with basic instructions and have to
update those instructions when the work gets closer to when the resource
needs to work on it.
In the Workload Balancer, tasks only show in teal = planning and green =
current. It would be helpful to distinguish "ready to start" tasks vs
"not ready to start" tasks. Resource Managers want to use the Workload
Balancer to see which tasks can be reassigned to help even out workloads
among the team.
We are trying to use predecessors to automate tasks from one step to the
next. However, the resource user cannot distinguish tasks where the
predecessor has been completed so they can start their task. Currently
when going to "Ready to Start", the tab has also included tasks in which
the predecessor is still pending.