hi, I have this question pending to support but I figured someone here
might have a faster answer. If I have this situation, here are the
resulting dates. Task 1, ASAP, predecessor=Task2 / fs / -10d = due
1/28/2019 Task 2, Must Finish On = due 2/10/2020 I think those are
pretty correct (task 1 starts -- and is due -- 10 days before task 2 is
due). If I put a parent task on top of that, I get this set of dates
instead. Parent Task, ASAP = due 2/10/2020 --Task 1, ASAP,
predecessor=Task2 / fs / -10...