Your achievements

Level 1

0% to

Level 2

Tip /
Sign in

Sign in to Community

to gain points, level up, and earn exciting badges like the new
Bedrock Mission!

Learn more

View all

Sign in to view all badges

HeidiSt1
HeidiSt1
Online

Badges

Badges
13

Accepted Solutions

Accepted Solutions
0

Likes Received

Likes Received
8

Posts

Posts
22

Discussions

Discussions
2

Questions

Questions
20

Ideas

Ideas
2

Blog Posts

Blog Posts
0
Top badges earned by HeidiSt1
Customize the badges you want to showcase on your profile
Re: We have a few tasks that happen on a Planned project before it moves to Current. Because tasks on a project in Planning don't show on the Lion/homepage we created a report that shows planned tasks two weeks out. - Workfront 19-04-2022
Very cool. Do I just look up Assignment Report? I wasnt aware of them. Any tips for setting up an assignment report. What is the difference?

Views

15

Likes

0

Replies

2
Allow Predecessors between two templates - Workfront 13-04-2022
Is there a way to connect templates with predecessors? We do a lot of our projects in EN and FR so when creating the FR project we spend time repeatedly connecting the EN & FR projects. It would help us be more efficient if they were connected already.

Views

7

Likes

2

Replies

0
Freeze the top row of the workload balancer - Workfront 13-04-2022
To freeze the upper row where the total of hours appear in the workload balancer. If one needs to scroll down, the total of hours disappears. We need to scroll down and up and down and up again to see if planned hours in a project isn’t overloading a day.

Views

6

Likes

2

Replies

0
We have a few tasks that happen on a Planned project before it moves to Current. Because tasks on a project in Planning don't show on the Lion/homepage we created a report that shows planned tasks two weeks out. - Workfront 13-04-2022
The challenge we have is that these tasks have multiple resources on them. So even if a resource marks their part complete it will show in their report until all resources mark their part complete. I have a filter that says dont show completed tasks but that task wont show completed until all resources mark their part done. Any ideas for filters or reporting features that will make this task disappear after the user has completed their part even if the other resources havent yet?

Views

15

Likes

0

Replies

4
Re: Registration is LIVE for Workfront's Skill Exchange Event on April 13th! - Workfront 13-04-2022
Can't wait to see the resources. Really want to see the Adoption Surveys.

Views

24

Likes

0

Replies

0
Can Workfront be used to create and store a Product Catalogue? - Workfront 08-12-2021
Can someone please confirm if they use Workfront as a product catalogue? We have team wanting to create a catalogue in SharePoint but we would like to use Workfront where the products are created? Most of the products we create through projects tracked in Workfront and Workfront provides better visibility.

Views

5

Likes

0

Replies

0
Re: Best practices for time tracking - Workfront 16-11-2021
We encourage people to track time as it is done or at least the same day. They can do it at task level or on the timesheet. If they leave it any later than the same day it might not be accurate.