Your Mail Date is a predecessor to line 34 so it's going to calculate on
line 34, not your in Market Date. Also, your In Market Date is set up to
Must Finish On so that could be an issue as well. However, I do run into
this every once in a while. I go up to the top right of the project,
select Project Actions and then Recalculate Timeline. Sometimes it still
doesn't work and I find there's some wonky setting in the task
somewhere. Wonky being a very technical term. Good luck! Kim
Ringelstetter C...