Barry, If the PM wants to extend the duration, even with fixed dates
constraint, the duration should be extended. In other words, override
the constraint. Alternatively, if the developers choose to keep the
fixed date constraint, the remaining tasks should be changed. Thanks,
Rochelle Dr. Rochelle L. Webb, CSM Interim Director, Project Management
Office MHMR Tarrant County Ft. Worth, Texas 817-569-4146