Your achievements

Level 1

0% to

Level 2

Tip /
Sign in

Sign in to Community

to gain points, level up, and earn exciting badges like the new
Bedrock Mission!

Learn more

View all

Sign in to view all badges

ElliotLe1
ElliotLe1
Offline

Badges

Badges
0

Accepted Solutions

Accepted Solutions
0

Likes Received

Likes Received
58

Posts

Posts
30

Discussions

Discussions
11

Questions

Questions
19

Ideas

Ideas
8

Blog Posts

Blog Posts
0
Top badges earned by ElliotLe1
Customize the badges you want to showcase on your profile
Re: Winter 2019 Meet up? - Workfront 21-10-2019
We will be there. Emma, agree about talking about the resource planning. I would like to talk about the new Modern View Scheduling and Workfront Experience. Looking forward to seeing everyone. Elliot Leson Synchrony Creative - The Studio (Company)

Views

76

Likes

0

Replies

0
Re: Winter 2019 Meet up? - Workfront 21-10-2019
Hi Amber. Please include me on. I'm part of the Syncrhony team. Thank you, Elliot Leson Creative Operations Manager The Studio Creative Team Synchrony T: +404-931-8687 E: Elliot.Leson@syf.com 4125 Windward Plaza Alpharetta, GA 30005

Views

76

Likes

0

Replies

0
Re: Best Practices-Governance in Workfront/Training - Workfront 20-06-2019
I would be interested in finding out info on this subject. Elliot Leson Synchrony Creative - The Studio (Company)

Views

30

Likes

0

Replies

0
Re: Resource Managers and Traffic Managers - Workfront Archived Groups 23-05-2019
Hi Tammie, See my bullets in red below and feel free to reach out to me with any questions. Always happy to jump on a call to assist. 1. Does anyone know how to implement restrictions for Plan users that do not and should not assign others' work? I haven't tried this, but I believe under Setup, Access Levels you may be able to add this rule? I could be wrong.. You can make it a best practice and reinforce the fact that these Plan users are not to assign work. 2. How do those of you multiple proj...

Views

18

Likes

0

Replies

0
Re: Community Booth at Leap! - Workfront Archived Groups 03-05-2019
I have that message on our Studio digital sign. Now if I could make that into a screen saver.... Elliot Leson Synchrony Creative - The Studio (Company)

Views

10

Likes

0

Replies

0
Re: Resource planning for Studio Spaces - Workfront 18-04-2019
Hi Elizabeth, Do the requests for booking a shoot location go through you? If so, thoughts on this solution? Create the following Program: Booking Calendar Projects: Shoot Locations (each location is a project, rolling up to program Booking Calendar) Resource: Possibly create a resource for booking the rooms called Studio Allocation? (hate to waste seat, but may be less expensive than paying for a plug in) From there, create a Calendar, "Booking Calendar" and add the projects, Studio Locations. ...

Views

11

Likes

0

Replies

0
Re: Winter 2019 Meet up? - Workfront 14-02-2019
I'm good for either April or May. We are in Alpharetta which is north of the city, so not sure how many people would want to travel up this way. Thank you, Elliot Elliot Leson Synchrony Creative - The Studio (Company)

Views

76

Likes

0

Replies

0
Kanban or Agile for Creative Team - Workfront 18-07-2018
Are any creative teams using Kanban or Agile in Workfront? If so, I would be interested in feedback on how this works with designers, copywriters and proofers. Thank you, Elliot Leson Synchrony Creative - The Studio

Views

21

Likes

3

Replies

3
Staffing Tool vs. Scheduling Tool - Workfront 29-06-2018
Is it possible to mirror the Staffing Tool with Scheduling Tool? The Planning licenses are having issues when trying to see resources available because not every project shows up in the Staffing tool. If the project does not belong to the Planner, they just see a gray bar with no hours allocated. It would be helpful if the Planners had the same view as the Resource Managers using the Scheduling tool. This helps to provide real time information. Even if the bar remains gray for permission reasons...

Views

10

Likes

9

Replies

1
Re: How does your company handle Split Billing? - Workfront 23-05-2018
Hi Jodie, In each task under the finance tab you are able to change the Cost Type to No Cost and Revenue Type to Not Billable. It would be best to set this up in templates if the non billable task is always non billable. Hope this helps. Let me know if you have any questions. Elliot Leson Synchrony Creative - The Studio