All, I am requesting Workfront to tweak the Algorithm for tracking
project conditions because we have a number of projects listed "At Risk"
when they aren't really at risk. The algorithm takes the percent
complete bar into a little more consideration than the planned start,
planned completion, and actual start date for tasks. To keep our
projects "On Target" We are telling our content developers to put 25,
50, or 75% in the task percent complete bar even though they may not be
that far along jus...