Hi Aya!

None of our users log hours/time in WF. For designers, I met with them to ask how long it takes to design certain types of assets. Their feedback was valuable as I built templates with design tasks that had the proper amount of days assigned to them.

For design projects, I look at the designers' schedules in the calendar function so I can see their current/upcoming bandwidth. I reference this when assigning them to projects and adjust the template as necessary in case additional (or less) days are necessary.

I hope this helps!