Hi ,
As per my experience with full vacuums it's definitely helps. we were facing issue where import jobs were taking too much time ~2/3hr and after running this vacuums there was significant reduce of time for import jobs ~ 30min. There are some best practice which you need to follow if you planning for the same. Also, timing for running this is also very important make sure heavy jobs either import or exports workflows are not running at that time and less number of active users.
Note : First run always take time so after first run schedule it on regular basis.
click this and you will find some best practice suggested by Adobe.