Hi,

When we provide the start date on adobe target test activity we need to push the test as activate or automatically it will goes LIVE/activate on production ?

Accepted Solutions (1)

Accepted Solutions (1)

Avatar

Avatar

Shruthi_N

Employee

Avatar

Shruthi_N

Employee

Shruthi_N
Employee

12-07-2018

Hi , When you schedule a test to start at a scheduled time, you will need to activate the test. It will then change the status to scheduled and then it will go Live at the scheduled time.

1526928_pastedImage_0.png

1526929_pastedImage_1.png

Answers (1)

Answers (1)

Avatar

Avatar

rajvib36266313

Avatar

rajvib36266313

rajvib36266313

12-07-2018

Okay great.I tried to create the sample test like that and it worked well. Thank you for your help.