Expand my Community achievements bar.

Task Status "Process Draft"

Avatar

Level 4

I''m working with support on an issue that I previously describe here: http://forums.adobe.com/thread/777349?tstart=0

I noticed with one of the process instances that encountered the issue, that the task status is set to "Process Draft" instead of the task status that I'm typically used to seeing when a task is assigned, which is "Process Created."

The only bit of info that I could find on "Process Draft" is here: http://help.adobe.com/en_US/livecycle/9.0/adminHelp/000354.html

Does anyone know why a task status would be set to "Process Draft"? And could that possibly be related to the problem I described in the other thread?

2 Replies

Avatar

Level 10

Draft = 1

Completed = 2

Assigned = 3

I hope these are the Task status.

tb_task table holds all the tasks;

Nith

Avatar

Level 2

If Workspace is used to work with tasks, then a task would have status "Process Draft" once a Workspace User has saved the task (via Save button, see image) but not yet completed the task.

save-button.PNG