Project Task Notification

khamat_bn

03-09-2020

Hi Folks,

 

I have created task in project window and assign to user. When user updates the task by adding comment or mark as complete I should have receive notification for the same. But it seems that only one notification is delivered. Which is for initial task creation. 

Also configuration for Notify on update and notify on complete is enabled 

khamat_bn_0-1599130837799.png

 

How can we receive update and complete notification too.

 

 

AEM 6.5

Accepted Solutions (0)

Answers (1)

Answers (1)

Vijayalakshmi_S

MVP

04-09-2020

Hi @khamat_bn,

Can you check if the OSGI component - com.day.cq.workflow.impl.email.TaskEMailNotificationService is active or it is in unsatisfied state. 

If it is unsatisfied, can you let know which service reference is unsatisfied. 

 

Notification should be in AEM Inbox or as an email if mail Id is configured for the assignee.