Hi there,

I want to set up an expiration date within the scheduler so the workflow stops once the campaign is finished but every time I try. Could you please send me an screenshot of how to that? Also on the expiration task what is the difference between:

Delay after task stats

Delay after a given date

Delay before a given date

Expiration calculated by script.

Thanks!

C

Accepted Solutions (1)

Accepted Solutions (1)

Avatar

Avatar

CIGM

Avatar

CIGM

CIGM

19-10-2017

Hi Florent,

I went for the delay after given date option.

Thanks,

Carlota

Answers (2)

Answers (2)

Avatar

Avatar

florentlb

Total Posts

1.1K

Likes

234

Correct Answer

239

Avatar

florentlb

Total Posts

1.1K

Likes

234

Correct Answer

239
florentlb

18-10-2017

Hi Carlota,

Sorry for the late answer. Can you share with us what solution you chose? What you describe would be set in the validity period settings of the Scheduler, described here in the docs: Order activities

Florent

Avatar

Avatar

CIGM

Avatar

CIGM

CIGM

18-10-2017

I have managed to do this myself. No need for reply.