Does Campaign Optimization/Pressure Rule needs the Delivery to be schedule in-order to implement the feature?

rajivkamathacc
Level 2
Level 2

I have been lately testing the Campaign Optimization feature. I noticed that if the Delivery isn't scheduled, the pressure rule exclusion isn't considered. As soon as I schedule the Delivery, I see recipients go through the Pressure rule typology.

 

Unfortunately, we mostly manually execute the Campaign. So wanted to confirm if Pressure Rule will only be implemented when the delivery is scheduled and wont when delivery are manually run.

 

Thanks in advance.

 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution
Jyoti_Yadav
Correct answer by
Community Advisor
Community Advisor

Hi @rajivkamathacc ,

 

Yes, you are right.

Pressure rule is applied on deliveries which are scheduled. It is mandatory step for pressure rule typologies.

Reason: There's a technical workflow which runs nightly and applies pressure rule.

 

Thanks,

Jyoti

View solution in original post

1 Reply
Jyoti_Yadav
Correct answer by
Community Advisor
Community Advisor

Hi @rajivkamathacc ,

 

Yes, you are right.

Pressure rule is applied on deliveries which are scheduled. It is mandatory step for pressure rule typologies.

Reason: There's a technical workflow which runs nightly and applies pressure rule.

 

Thanks,

Jyoti

View solution in original post