Hi Team, 

 

We have a requirement of moving bulk offers around ~2k offers from Stage / Dev enviorment to PROD.

When I tried moving a sample one from existing stage environment to Dev box ; what i noticed is the offer that I took was approved and was published in Live environment. 

 

So, if we move this offer (which is in design environment)  from stage to Dev, it will again ask for the approvals and I assume post approval the offers gets published to Live environment. 

 

Since we have around 2K offers approving each manually is a tedious job, so wanted some inputs, should it be ok if we move the Live offer package or is there any other better way to do the bulk movement of offers from one environment to another. 

 

Thanks,
Adithya

Accepted Solutions (1)

Accepted Solutions (1)

Avatar

Avatar

wodnicki

MVP

Avatar

wodnicki

MVP

wodnicki
MVP

07-10-2020

Hi,

 

Use mass update to mark everything approved (there are 4 fields for approval in offers?), then publish per usual.

 