Expand my Community achievements bar.

Join us at Adobe Summit 2024 for the Coffee Break Q&A Live series, a unique opportunity to network with and learn from expert users, the Adobe product team, and Adobe partners in a small group, 30 minute AMA conversations.
SOLVED

In workspace, how to set to get "Full Week" data only?

Avatar

Level 8
Level 8

The date duration is set to "This Quarter", dimension by "Week".

But the data will be refreshed once the new week reaches.

Is there a way to get new week data only when the full week completes?

H_L_0-1604410972366.png

 

Asking this is because the dashboard is scheduled a weekly delivery, according to current situation, we either will not get the full data if the schedule is earlier (last full week not completes), or will not get the full data for the current new week on the "number" area.

H_L_1-1604411096938.png

 

Please help to share your ideas.

Thanks for advance.

1 Accepted Solution

Avatar

Correct answer by
Employee Advisor

Try creating a Custom Date Range such as this:

Khurshid_Alam_0-1604435334148.png

 

View solution in original post

3 Replies

Avatar

Level 10

Set a rolling date range in the panel to include only past weeks.

 
Best wishes,
Andrey Osadchuk | Launch Inspector, Analytics Connector, Bookmarks

Avatar

Correct answer by
Employee Advisor

Try creating a Custom Date Range such as this:

Khurshid_Alam_0-1604435334148.png