I scheduled the report from workspace (and it comes to my email), but I do not see it in Components > Scheduled reports. What should I do?

2 Replies

Avatar

Community Advisor

Hello Kat Beni,

You should navigate to Components > Scheduled Projects to access Workspace Projects rather than Components > Scheduled reports.

Thank You!

Arun

Avatar

Level 5

Hi,

In Analytics > Components > Scheduled Projects, if you click on the blue title of the project, you should be able to edit the scheduled project to add new recipients. There is no Edit button, you just click on the title.

Reference: Scheduled Projects